Tool guide / Home projects

Measure square footage, order concrete, and add up hours

Most home projects go wrong at the measuring stage: a flooring order that comes up a box short, a concrete pour that runs out at the last corner, or a time sheet that adds 7:45 and 8:30 as 16.15 hours. The Square Footage Calculator, Concrete Calculator, and Time Calculator run in your browser, and every number below comes from the same code. Nothing you type is sent anywhere.

1. Square footage for a whole floor

Split an open or L-shaped space into rectangles, measure each one, and add them up. Subtract anything that will not be covered, such as a kitchen island or a fireplace hearth. Measurements in feet and inches work as typed: 16'4" is 16.33 feet, not 16.4.

AreaSquare feet
Living room223.2
Dining room132
Kitchen147
Hallway63
− Kitchen island18

The floor measures 547.2 sq ft. Flooring is sold in boxes and cut at every wall, so order 10% extra for a straight layout (601.9 sq ft) and about 15% for a diagonal or herringbone pattern (629.3 sq ft). At $4.25 per square foot, the straight layout costs about $2,558.26 in material.

Open this floor in the Square Footage Calculator

The same total converts to 66.9 square yards for carpet, which is often priced per square yard, or 55.9 m². For paint, measure the wall perimeter times the ceiling height instead, and subtract about 20 sq ft per door and 15 sq ft per window.

2. How much concrete a patio needs

Concrete is ordered by volume: length × width × thickness. A 12 × 16 ft patio poured 4 inches thick is 70.4 cubic feet with 10% extra for uneven ground and spillage, or 2.61 cubic yards. Ready-mix trucks deliver in quarter-yard steps, so the order is 2.75 yd³, about $430.22 at $165 a yard before delivery fees.

Open this patio in the Concrete Calculator

ThicknessCubic yards80 lb bags
3.5 in2.28103
4 in2.61118
5 in3.26147
6 in3.91176

Mixing by hand, the same patio takes 118 80 lb bags or 157 60 lb bags. Past about a cubic yard, bagged concrete costs more and takes far longer than a ready-mix delivery. Going from 4 to 6 inches thick adds half again to the volume, so only thicken the slab where it carries vehicles.

Post holes are cylinders. Twelve fence posts in 10-inch holes 3½ feet deep need 25.2 cubic feet with 10% extra, or 42 80 lb bags. The calculator subtracts nothing for the post itself, which leaves a small safety margin.

Open these post holes in the Concrete Calculator

3. Add hours and minutes without decimal mistakes

Time does not add like decimals: 7:45 + 8:10 is 15:55, not 15.55 hours, and 15:55 is 15.92 decimal hours. A week of shifts of 7:45, 8h 10m, 6:30 plus 1:15, 8:20, and 7:05 adds to 39:05, which is 39.08 hours on an invoice or time sheet.

Open this week in the Time Calculator

Switch to reading 18:05 as minutes and seconds to total video or audio lengths. A course with lessons of 4:32, 18:05, 22:47, 16:30, and 31:12 runs 1:33:06; starting at 7:00 PM it ends at 8:33:06 PM. Watched at 1.25× speed, multiply by 0.8 to get 1:14:28.8.

Open this course in the Time Calculator

For clock-in and clock-out times with breaks, overtime, and pay, use the Hours Calculator instead.

Related tools

Convert feet, meters, and cubic measures with the Unit Converter, price a mortgage or renovation loan with the Mortgage Calculator and Loan Calculator, and estimate running costs with the Electricity Cost Calculator. These calculators also run in the Mer Tools extension.